COMMISSIONING STARTS AT SHELFORD LEACHATE TREATMENT PLANT
Phoenix Engineering construction team has handed over the refurbished Viridor Shelford Leachate Treatment Plant to the commissioning team. Plant tests and calibrations have been underway with process commissioning having starting 23rd April 2016. The refurbished plant is now CIRIA 736
SHELFORD LEACHATE TREATMENT PLANT
MEICA fit out of the Shelford Leachate Treatment Plant is going well and is on programme. Commissioning is planned for April/May 2016.
KEEPING THE STINK UNDER CONTROL
Our Process Director Howard Robinson has helped a waste management company in South Africa tackle its hydrogen sulphide odour problems at its landfill site using simple, innovative and robust treatment technologies.
ARDLEY LTP REFURBISHMENT WORKS
Construction of the new automated sodium hydroxide and anti-foam dosing system at the Ardley Landfill Site Leachate Treatment is well underway. Commission is being undertaken this week.
PHOENIX HOUSE
Construction of our new office and fabrication unit is well underway. We expect to be in our new premises between June and August this year.
PILSWORTH LTP SODIUM HYDROXIDE DOSING SYSTEM UPGRADE
The automated sodium hydroxide dosing system upgrade at Pilsworth Landfill LTP is complete and fully operational. Phoenix is now developing a safe means of decontamination and removal of the old dosing system and storage tanks. This work is planned to